Demo Questions

Question 1
Which of the following tools should be used when a team is generating and prioritizing a list of options that include highly controversial issues?
  1. Brainstorming
  2. Affinity diagrams
  3. Nominal group technique
  4. 5 whys
Correct answer: C
Question 2
The primary factor in the successful implementation of six sigma is to have
  1. the necessary resources
  2. the support and leadership of top management
  3. explicit customer requirements
  4. a comprehensive training program
Correct answer: B
Question 3
Which of the following tools would be most appropriate for collecting data to study the symptoms of a problem?
  1. Check sheet
  2. Flow diagram
  3. Force-field analysis
  4. Activity network diagram
Correct answer: A
Question 4
Positional, cyclical, and temporal variations are most commonly analyzed in
  1. SPC charts
  2. multi-vari charts
  3. cause and effect diagrams
  4. run charts
Correct answer: B
Question 5
The most important aspect of functional requirements is that they
  1. describe a single, measurable performance
  2. describe how a product or service should operate
  3. be traceable to the voice of the customer
  4. provide upper and lower performance limits
Correct answer: C
Question 6
Which of the following control charts is most appropriate for monitoring the number of defects on different sample sizes?
  1. u
  2. np
  3. c
  4. p
Correct answer: A
Question 7
Which of the following is most important in evaluating and understanding design intent?
  1. Identifying the functional requirement
  2. Brainstorming failure modes
  3. Conducting computer simulations
  4. Developing FMEA
Correct answer: A
Question 8
If a process follows an exponential distribution with a mean of 25, what is the standard deviation for the process?
  1. 0.4
  2. 5.0
  3. 12.5
  4. 25.0
Correct answer: D
Question 9
Which of the following activities is value-added?
  1. Setup
  2. Process
  3. Storage
  4. Inspection
Correct answer: B
Question 10
A black belt plans to test the performance of workers before and after training. Which of the following hypothesis tests should be used to determine whether the training actually improved the workers’ performance?
  1. 2-sample z test
  2. 2-sample t test
  3. Paired t test
  4. F test
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES