Demo Questions

Question 1
Which product records any project outcomes perceived as negative by stakeholders?

  • A: Business Case
  • B: Project Plan
  • C: Communication Management Strategy
  • D: Project Product Description



Question 2
What is the definition of a project outcome?

  • A: A measurable improvement that is perceived as an advantage by one or more stakeholders
  • B: The reason for the project
  • C: The result of the change derived from using the project's outputs
  • D: The project's specialist products.



Question 3
Which is NOT a purpose of a Benefits Review Plan?

  • A: Define the period over which the cost-benefit analysis will be based
  • B: Describe how to measure the performance of the project's products in operational use
  • C: Define the scope, timing and ownership of the benefit reviews required
  • D: Describe how to measure and confirm any benefits that are to be realised after the project is closed



Question 4
Which product documents the information needed to demonstrate continued business justification?

  • A: Business Case
  • B: Communication Management Strategy
  • C: Project Product Description
  • D: Quality Management Strategy



Question 5
What is an off-specification?

  • A: A new requirement
  • B: A quality tolerance
  • C: A type of issue
  • D: A major risk



Question 6
Which is a type of issue? 

  • A: A lesson
  • B: A request for change
  • C: An Exception Report
  • D: A risk with an estimated high impact



Question 7
What needs to be in place to ensure effective issue and change control?

  • A: Configuration management system
  • B: Manage by exception
  • C: Quality planning
  • D: Information needs for stakeholders



Question 8
Which should be funded by a change budget?

  • A: Increase in agreed scope
  • B: Initiation stage 
  • C: Change Authority
  • D: Handover activities



Question 9
Which should be funded from a change budget?

  • A: The Starting up a Project process
  • B: A fallback plan
  • C: An agreed change to the scope of a project
  • D: A change to a plan, within allocated tolerances, due to poor estimating



Question 10
Which is the Issue Register NOT used for?

  • A: Capture external events that are impacting a stage
  • B: Record information about a deviation in stage tolerance
  • C: Capture any threats or opportunities that might have an impact on a stage 
  • D: Record any problems identified when authorizing a Work Package








ProfExam
PROFEXAM WITH A 20% DISCOUNT

You can buy ProfExam with a 20% discount..

Get Now!


HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen



HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset