Download PRINCE2 Foundation.PRINCE2-Foundation.ActualTests.2021-11-30.355q.vcex

Vendor: PRINCE2
Exam Code: PRINCE2-Foundation
Exam Name: PRINCE2 Foundation
Date: Nov 30, 2021
File Size: 239 KB
Downloads: 2

How to open VCEX files?

Files with VCEX extension can be opened by ProfExam Simulator.

Demo Questions

Question 1
Which product records any project outcomes perceived as negative by stakeholders?
  1. Business Case
  2. Project Plan
  3. Communication Management Strategy
  4. Project Product Description
Correct answer: A
Question 2
What is the definition of a project outcome?
  1. A measurable improvement that is perceived as an advantage by one or more stakeholders
  2. The reason for the project
  3. The result of the change derived from using the project's outputs
  4. The project's specialist products.
Correct answer: C
Question 3
Which is NOT a purpose of a Benefits Review Plan?
  1. Define the period over which the cost-benefit analysis will be based
  2. Describe how to measure the performance of the project's products in operational use
  3. Define the scope, timing and ownership of the benefit reviews required
  4. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Correct answer: A
Question 4
Which product documents the information needed to demonstrate continued business justification?
  1. Business Case
  2. Communication Management Strategy
  3. Project Product Description
  4. Quality Management Strategy
Correct answer: A
Question 5
Which is NOT a purpose of a Benefits Review Plan?
  1. Define the period over which the cost-benefit analysis will be based
  2. Describe how to measure the performance of the project's products in operational use
  3. Define the scope, timing and ownership of the benefit reviews required
  4. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Correct answer: A
Question 6
What is an off-specification?
  1. A new requirement
  2. A quality tolerance
  3. A type of issue
  4. A major risk
Correct answer: C
Question 7
Which is a type of issue? 
  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact
Correct answer: B
Question 8
Which is a typical core activity within configuration management?
  1. Quality assurance
  2. Risk management
  3. Verification and audit
  4. Progress reporting
Correct answer: C
Question 9
Which is a typical core activity within configuration management?
  1. Issue management 
  2. Quality inspection
  3. Identification
  4. Preparation
Correct answer: C
Question 10
What needs to be in place to ensure effective issue and change control?
  1. Configuration management system
  2. Manage by exception
  3. Quality planning
  4. Information needs for stakeholders
Correct answer: A
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!