Question 1
Which document describes the necessary information to determine if a project is worth the required investment?
  1. Cost baseline
  2. Service level agreement
  3. Memorandum of understanding
  4. Business case
Correct answer: D
Question 2
Which item is an example of personnel assessment?
  1. Resource calendar
  2. Tight matrix
  3. Team-building activity
  4. Focus group
Correct answer: D
Question 3
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
  1. Feedback analysis
  2. Stakeholder analysis
  3. Communication management plan
  4. Stakeholder management plan
Correct answer: D
Question 4
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
  1. Project Risk Management
  2. Project Human Resource Management
  3. Project Scope Management
  4. Project Stakeholder Management
Correct answer: D
Question 5
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
  1. Stakeholder register
  2. Scope management plan
  3. Stakeholder management plan
  4. Project charter
Correct answer: A
Question 6
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
  1. Responses
  2. Appetite
  3. Tolerance
  4. Attitude
Correct answer: A
Question 7
An output of the Manage Stakeholder Engagement process is:
  1. change requests
  2. enterprise environmental factors
  3. the stakeholder management plan
  4. the change log
Correct answer: A
Question 8
Which process numerically analyzes the effect of identified risks on overall project objectives?
  1. Plan Risk Management
  2. Plan Risk Responses
  3. Perform Quantitative Risk Analysis
  4. Perform Qualitative Risk Analysis
Correct answer: C
Question 9
The process of prioritizing risks for further analysis or action is known as:
  1. Plan Risk Management.
  2. Plan Risk Responses.
  3. Perform Qualitative Risk Analysis.
  4. Perform Quantitative Risk Analysis.
Correct answer: C
Question 10
Stakeholder satisfaction should be managed as a key project:
  1. Benefit
  2. Initiative
  3. Objective
  4. Process
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!