Demo Questions

Question 1
Which role is responsible for creating and communicating the vision for the programme?
  1. Programme office
  2. Business change manager
  3. Programme manager
  4. Senior responsible owner
Correct answer: C
Explanation:
Reference: https://www.axelos.com/news/blogs/january-2021/msp-vision-statement-programmes-with-purpose
Reference: https://www.axelos.com/news/blogs/january-2021/msp-vision-statement-programmes-with-purpose
Question 2
Under which heading in the POTI model should the current performance level of an operational area be recorded?
  1. Process
  2. Organization
  3. Technology
  4. Information
Correct answer: A
Explanation:
Reference: https://pmtips.net/article/poti-model-programme-blueprints
Reference: https://pmtips.net/article/poti-model-programme-blueprints
Question 3
Which is a feature of an effective programme organization?
  1. Clear accountability for each management role
  2. A business case agreed by the stakeholders
  3. Monitored and controlled programme changes
  4. A quality assured configuration management system
Correct answer: C
Question 4
Which is a description of a programme resource?
  1. The objective of a programme
  2. A process to control a programme
  3. A logical grouping of projects within a programme
  4. An input required by a programme
Correct answer: D
Question 5
Which document should be used to provide guidance on the standards that should be followed when producing outputs?
  1. Projects Dossier
  2. Project Brief
  3. Programme Blueprint
  4. Programme Brief
Correct answer: B
Explanation:
Reference: https://www.simplilearn.com/overview-of-planning-and-control-tutorial
Reference: https://www.simplilearn.com/overview-of-planning-and-control-tutorial
Question 6
Which risk response encourages collaboration on risk management activities?
  1. Avoid
  2. Reduce
  3. Share
  4. Prepare contingent plans
Correct answer: C
Explanation:
Reference: https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial
Reference: https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial
Question 7
Which is a characteristic of a programme?
  1. It manages the planning, monitoring and control of projects
  2. It co-ordinates, directs and oversees the implementation of a set of related projects and activities
  3. It delivers one or more outputs in accordance with an agreed business case
  4. It defines an organization’s approach to achieving its corporate objectives in a given area of business
Correct answer: B
Explanation:
Reference: https://repmt.com/learning-paths/msp-managing-successful-programmes/
Reference: https://repmt.com/learning-paths/msp-managing-successful-programmes/
Question 8
Which is NOT a purpose of a Blueprint?
  1. Provide a basis for modelling benefits
  2. Provide a usable basis for designing the Projects Dossier
  3. Ensure coherence of the entire future state
  4. Describe how to get to the future state
Correct answer: D
Explanation:
Reference: https://www.axelos.com/news/blogs/may-2017/the-blueprint-a-cornerstone-of-programmes-and-msp
Reference: https://www.axelos.com/news/blogs/may-2017/the-blueprint-a-cornerstone-of-programmes-and-msp
Question 9
Which role would be MOST LIKELY to initiate assurance reviews of project performance?
  1. Senior responsible owner
  2. Programme manager
  3. Business change manager
  4. Programme office
Correct answer: B
Question 10
Which of the following statements about a vision-led programme is true?  
  1. Tends to be top down in approach, with cross functional implications  
  2. Evolves from concurrent projects
  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true  
  4. Neither 1 or 2 is true
Correct answer: A
Explanation:
Reference: https://repmt.com/learning-paths/msp-managing-successful-programmes/
Reference: https://repmt.com/learning-paths/msp-managing-successful-programmes/
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!