Demo Questions

Question 1
What is the main reason why reviews are especially beneficial in the above-mentioned scenario?
  1. They ensure a common understanding of the product.
  2. They find defects early.
  3. They enhance project communication.
  4. They can be performed without exercising the code.
Correct answer: D
Question 2
The introduction of reviews and inspections has often failed as a process improvement action.   Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail.
  1. Process ownership and experienced moderators who drive the inspection process.
  2. Management support
  3. Training of those involved
  4. The availability of stands and processes
  5. Usage of a more traditional software development lifecycle
  6. Alignment with software process improvement
  7. Using a reference model, e.g. TMMi
Correct answer: ABC
Question 3
IEEE 1028 also defines “management review” as a type of review. What is the main purpose of a management review?
  1. Align technical concepts during the design phase
  2. Establish a common understanding of requirements
  3. Provide independent evaluation of compliance to processes, regulations, standards etc.
  4. To monitor progress, assess the status of a project, and make decisions about future actions
Correct answer: D
Question 4
Which of the following is an example of testing as part of the requirements specification phase?
  1. A requirements review meeting
  2. A business analyst eliciting requirements
  3. Performing acceptance tests against requirements
  4. A test report showing requirements coverage
Correct answer: A
Question 5
Select THREE issues from the options provided that should at least be raised.
  1. Has there been sufficient comparison of tools?
  2. What are the problems we are trying to address?
  3. Do we have a set of tool requirements to validate the tool against?
  4. How will the implementation be organized?
  5. Which project will be selected to perform the tool pilot?
  6. Is customized training available?
  7. How will the change process be managed?
Correct answer: ABC
Question 6
Which of the following would you least expect to form part of the analysis of initial tool costs?
  1. Integration with other tools
  2. Learning time required to use the new tool
  3. Tool portability
  4. Evaluation of suitable tools
Correct answer: C
Question 7
Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year?  
i. We do not have a clear understanding of the requirements from a customer perspective. 
ii. We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product. 
iii. We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations. 
iv. The company test strategy does not fit well within the V life cycle model.
  1. (i) and (ii)
  2. (i) and (iv)
  3. (ii) and (iii)
  4. (ii) and (iv)
Correct answer: A
Question 8
Which of the following is a characteristic of good testing in any life cycle model?
  1. Analysis and design of tests begins as soon as development is completed.
  2. Some, but not all, development activities have corresponding test activities.
  3. Each test level has test objectives specific to that level.
  4. All document reviews involve the development team.
Correct answer: C
Question 9
Which of the following would you expect to see in the master test plan?
  1. A description of how the test cases are cross-referenced to requirements in the test management tool.
  2. A detailed identification of the resources that will carry out structural testing in the first iteration.
  3. The test approach that will be applied at system integration testing.
  4. A list of the names of the testers who will carry out the performance testing for the final iteration.
Correct answer: C
Question 10
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks?
  1. The skills and experience of developers to correct the failures.
  2. The standards used for the requirements specification.
  3. The metrics recorded from testing the capture-replay tool.
  4. The number of testers in the company and their grade.
Correct answer: C
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!