Question 1
What does the Scrum Development Team attempt to develop at every Sprint?
  1. A product that is ready for customer delivery
  2. A completed Sprint Backlog
  3. A product that is ready for QA and/or QC testing
  4. A product increment that is potentially-ready for customer delivery
Correct answer: D
Explanation:
D: 2 - Mosted
D: 2 - Mosted
Question 2
What is the recommended size for a Development Team?
  1. 6, +3 or -3
  2. 9
  3. 6
  4. 7, +2 or -2
Correct answer: D
Explanation:
A: 1 - Mosted
A: 1 - Mosted
Question 3
Who is ultimate responsible for the Product Backlog item estimates?
  1. The Development Team
  2. Scrum Master
  3. Stakeholders
  4. Project Owner
Correct answer: D
Question 4
When is the Sprint Backlog created?
  1. At the beginning of the project
  2. Prior to the Sprint Planning meeting
  3. During the Sprint
  4. During the Sprint Planning meeting
Correct answer: B
Question 5
Which of the following is NOT part of the Sprint?
  1. The product is released to customers after each Sprint
  2. The principal goal for a Sprint is to produce release-quality increments in functionality
  3. Releases usually incorporate the result of multiple Sprints
  4. Occur at times dictated by customer and business needs
Correct answer: A
Explanation:
D: 1 - Mosted
D: 1 - Mosted
Question 6
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
  1. The development team cannot meet their Sprint commitment to complete work if requirements are changing
  2. A Sprint cycle is not enough time for senior management review and approve changes
  3. This forces Product Owners to focus on what is really important for the team to develop.
  4. The development team must be able to limit the Product Owner authority
Correct answer: C
Explanation:
C: 1 - Mosted
C: 1 - Mosted
Question 7
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos -
Sprint 2: 11 pontos -
Sprint 3: 15 pontos -
Sprint 4: 14 pontos -
Sprint 5: 15 pontos -
Sprint 6: 10 pontos -
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
  1. 6
  2. 5
  3. 4
  4. 3
Correct answer: B
Question 8
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
  1. The development team should negotiate with the Product Owner on the definition of "done".
  2. The development team should work the extra 8 hours to complete their commitment to the Product Owner
  3. The development team should place the two Product Backlog items back onto the Product Backlog
  4. The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first
Correct answer: C
Explanation:
C: 3 - Mosted
C: 3 - Mosted
Question 9
Which statement below best describes the primary objective of the Sprint Review?
  1. The primary objective of the Sprint Review is to demo the Sprint work for Senior Management
  2. The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Product Owner(s) on the work completed in the Sprint
  3. The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Scrum Mater on the work completed in the Sprint
  4. The primary objective of the Sprint Review is to demo the Sprint work and to recommend ways to work better in the Sprint.
Correct answer: B
Question 10
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
  1. 1, 2, and 3
  2. 1 and 2 only
  3. The entire company
  4. 1 only
Correct answer: B
Question 11
What is the maximum amount of time that the team should spend in the daily scrum?
  1. As long as it takes
  2. 1 hour
  3. 45 minutes
  4. 15 minutes
  5. 15 minutes, proportionally less for shorter Sprints
Correct answer: D
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!