Question 1
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
  1. Apply the SDLC process.
  2. Establish a program.
  3. Consult the CCB.
  4. Use different frameworks.
Correct answer: B
Explanation:
B: 5 - Mosted
B: 5 - Mosted
Question 2
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
  1. Ishikawa diagram
  2. Scatter diagram
  3. Pareto chart
  4. Decision tree
Correct answer: C
Explanation:
C: 11 - Mosted
C: 11 - Mosted
Question 3
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
  1. Status report
  2. Project plan
  3. Change log
  4. Meeting minutes
Correct answer: D
Explanation:
D: 6 - Mosted
D: 6 - Mosted
Question 4
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
  1. Synchronous
  2. Informal
  3. Asynchronous
  4. Formal
Correct answer: A
Explanation:
A: 3 - Mosted
A: 3 - Mosted
Question 5
Which of the following activities would a project manager perform during the closing phase? (Choose three.)
  1. Lessons learned
  2. Risk analysis
  3. Removing resources
  4. Acquiring resources
  5. Statement of work sign-off
  6. Stakeholder analysis
  7. Removing access
Correct answer: ACG
Explanation:
ACG: 18 - Mosted
ACG: 18 - Mosted
Question 6
Which of the following describes three-tier architecture?
  1. Conceptual, design, and implementation stages
  2. Presentation, application, and data processing
  3. Network, software, and security
  4. Development, testing, and production environment
Correct answer: B
Explanation:
B: 8 - MostedD: 2
B: 8 - MostedD: 2
Question 7
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:
Based on the chart, which of the following is the current status of the project?
  1. Behind schedule and over budget
  2. Behind schedule and under budget
  3. Ahead of schedule and over budget
  4. Ahead of schedule and under budget
Correct answer: A
Explanation:
A: 13 - Mosted
A: 13 - Mosted
Question 8
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
  1. Smoke testing
  2. Regression testing
  3. Unit testing
  4. User acceptance testing
Correct answer: B
Explanation:
B: 5 - Mosted
B: 5 - Mosted
Question 9
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
  1. Evaluating the project
  2. Releasing the resources
  3. Closing the contracts
  4. Reconciling the budget
Correct answer: D
Explanation:
A: 9D: 16 - Mosted
A: 9D: 16 - Mosted
Question 10
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
  1. Allocate resources.
  2. Determine the project budget.
  3. Develop a communication plan.
  4. Establish baselines.
Correct answer: A
Explanation:
A: 14 - MostedD: 3
A: 14 - MostedD: 3
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!