Download CompTIA Project+.PK0-005.VCEplus.2024-08-26.107q.vcex

Vendor: CompTIA
Exam Code: PK0-005
Exam Name: CompTIA Project+
Date: Aug 26, 2024
File Size: 501 KB
Downloads: 1

How to open VCEX files?

Files with VCEX extension can be opened by ProfExam Simulator.

Demo Questions

Question 1
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
  1. Business requirement
  2. Client statement of work
  3. Formal contract
  4. Project charter
Correct answer: C
Explanation:
A formal contract is a legal document that defines the terms and conditions of the agreement between the project parties, such as the scope, schedule, budget, quality, deliverables, roles and responsibilities, payment methods, and dispute resolution mechanisms. A formal contract is essential for external projects, especially when there is an exchange of money involved, to protect the interests and rights of both parties and to ensure mutual understanding and compliance. A formal contract is different from a business requirement, which is a statement of the needs and expectations of the customer or stakeholder for the project outcome. A formal contract is also different from a client statement of work, which is a document that describes the work to be performed, the deliverables to be provided, and the acceptance criteria to be met by the project vendor or contractor. A formal contract is also different from a project charter, which is a document that authorizes the project and provides the high-level information about the project objectives, scope, stakeholders, and project manager. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 4: Project Integration Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 4: Project Integration Management2; 11 Essential Documents To Use as a Project Manager3
A formal contract is a legal document that defines the terms and conditions of the agreement between the project parties, such as the scope, schedule, budget, quality, deliverables, roles and responsibilities, payment methods, and dispute resolution mechanisms. A formal contract is essential for external projects, especially when there is an exchange of money involved, to protect the interests and rights of both parties and to ensure mutual understanding and compliance. A formal contract is different from a business requirement, which is a statement of the needs and expectations of the customer or stakeholder for the project outcome. A formal contract is also different from a client statement of work, which is a document that describes the work to be performed, the deliverables to be provided, and the acceptance criteria to be met by the project vendor or contractor. A formal contract is also different from a project charter, which is a document that authorizes the project and provides the high-level information about the project objectives, scope, stakeholders, and project manager. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 4: Project Integration Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 4: Project Integration Management2; 11 Essential Documents To Use as a Project Manager3
Question 2
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
  1. Smoke test
  2. Stress test
  3. Penetration test
  4. Regression test
Correct answer: A
Question 3
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
  1. Dashboard
  2. Gantt chart
  3. Work breakdown structure
  4. Requirements Traceability Matrix
Correct answer: A
Explanation:
A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.
A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.
Question 4
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
  1. Critical paths
  2. Resources
  3. Milestones
  4. Work breakdown structures
Correct answer: C
Explanation:
Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task.Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task.
Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
Question 5
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
  1. Decline because it is not included in the project scope.
  2. Assess the impact of the request and create a change request
  3. Create new functional and non-functional requirements for mobile devices.
  4. Revise the baseline of the project plan by adding the new requirements.
Correct answer: B
Explanation:
Assess the impact of the request and create a change request. The project manager should assess the impact of the request and create a change request in response to the stakeholder asking to add mobile device functionality to a project that is on track to be completed under budget and ahead of schedule. A change request is a document that formally proposes and records a modification or addition to some aspect of a project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and justify the need and rationale for the change and its implications on the project objectives and deliverables. A change request also helps to initiate the change control process, which involves reviewing, approving, implementing, and monitoring the change12
Assess the impact of the request and create a change request. The project manager should assess the impact of the request and create a change request in response to the stakeholder asking to add mobile device functionality to a project that is on track to be completed under budget and ahead of schedule. A change request is a document that formally proposes and records a modification or addition to some aspect of a project, such as scope, schedule, cost, quality, or resources. A change request can help to communicate and justify the need and rationale for the change and its implications on the project objectives and deliverables. A change request also helps to initiate the change control process, which involves reviewing, approving, implementing, and monitoring the change12
Question 6
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
  1. A risk budget
  2. A risk impact
  3. A change request
  4. A contingency plan
Correct answer: D
Explanation:
The project manager should have generated a contingency plan first to alleviate the impact of this issue prior to deployment where a major malfunction resulted in an inoperative product condition during a code implementation. A contingency plan is a plan that outlines alternative courses of action or strategies to deal with potential problems or risks that may occur during a project. A contingency plan can help to prevent or minimize the negative impacts of unforeseen events or issues on the project objectives and deliverables and ensure business continuity and stability.
The project manager should have generated a contingency plan first to alleviate the impact of this issue prior to deployment where a major malfunction resulted in an inoperative product condition during a code implementation. A contingency plan is a plan that outlines alternative courses of action or strategies to deal with potential problems or risks that may occur during a project. A contingency plan can help to prevent or minimize the negative impacts of unforeseen events or issues on the project objectives and deliverables and ensure business continuity and stability.
Question 7
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
  1. Procurement
  2. Communication
  3. Quality assurance
  4. Risk
Correct answer: C
Explanation:
The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and documents the standards, criteria, methods, activities, and tools for ensuring and verifying that the quality requirements and expectations of a project are met. A quality assurance plan can help to improve the quality of the project processes and deliverables and prevent or reduce defects or errors.
The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and documents the standards, criteria, methods, activities, and tools for ensuring and verifying that the quality requirements and expectations of a project are met. A quality assurance plan can help to improve the quality of the project processes and deliverables and prevent or reduce defects or errors.
Question 8
A PM learns about some communication issues with different stakeholders and team members.
Which of the following should the PM do NEXT?
  1. Escalate the communication issues.
  2. Implement a communication platform.
  3. Review the communication plan.
  4. Talk with the head of the PMO.
Correct answer: C
Explanation:
The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.
The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.
Question 9
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
  1. The ticket system provided access by default without any approval.
  2. The project manager did not perform proper project planning.
  3. The system is lacking proper access controls.
  4. Sensitive data was incorrectly classified during the audit process.
Correct answer: C
Explanation:
The system is lacking proper access controls if a third-party vendor was able to see secured project information in a recently implemented system that resulted in a fine for the organization. Access controls are security mechanisms that regulate who or what can view, use, or modify data or resources in a system or network. Access controls typically involve authentication and authorization processes that verify the identity and permissions of users or devices before granting them access. Access controls can help to protect data confidentiality, integrity, and availability and prevent unauthorized access, misuse, or theft12
The system is lacking proper access controls if a third-party vendor was able to see secured project information in a recently implemented system that resulted in a fine for the organization. Access controls are security mechanisms that regulate who or what can view, use, or modify data or resources in a system or network. Access controls typically involve authentication and authorization processes that verify the identity and permissions of users or devices before granting them access. Access controls can help to protect data confidentiality, integrity, and availability and prevent unauthorized access, misuse, or theft12
Question 10
Which of the following is the best example of a breach of physical security?
  1. System user IDs being used by multiple individuals
  2. Printers that do not request user authentication
  3. Developers having full access to both development and production environments
  4. Project documentation that is only kept on a removable device
Correct answer: D
Explanation:
A breach of physical security is an unauthorized access or damage to physical assets, such as equipment, data, or personnel. Project documentation that is only kept on a removable device is the best example of a breach of physical security, because it exposes sensitive information to theft, loss, or corruption. If the removable device is not encrypted or protected, anyone who obtains it can access the project documentation and compromise the project integrity, confidentiality, or availability. Therefore, project documentation should be stored in a secure location, backed up regularly, and protected by access controls and encryption.The other options are not examples of physical security breaches, but rather logical or administrative security breaches. System user IDs being used by multiple individuals is a violation of the principle of least privilege and accountability, which could lead to unauthorized access or misuse of system resources. Printers that do not request user authentication is a lack of proper access control, which could allow unauthorized printing or retrieval of confidential documents. Developers having full access to both development and production environments is a violation of the principle of separation of duties and environments, which could introduce errors, conflicts, or malicious code into the production system. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Security Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 9: Security Management2; Types of Security Breaches: Physical and Digital3
A breach of physical security is an unauthorized access or damage to physical assets, such as equipment, data, or personnel. Project documentation that is only kept on a removable device is the best example of a breach of physical security, because it exposes sensitive information to theft, loss, or corruption. If the removable device is not encrypted or protected, anyone who obtains it can access the project documentation and compromise the project integrity, confidentiality, or availability. Therefore, project documentation should be stored in a secure location, backed up regularly, and protected by access controls and encryption.
The other options are not examples of physical security breaches, but rather logical or administrative security breaches. System user IDs being used by multiple individuals is a violation of the principle of least privilege and accountability, which could lead to unauthorized access or misuse of system resources. Printers that do not request user authentication is a lack of proper access control, which could allow unauthorized printing or retrieval of confidential documents. Developers having full access to both development and production environments is a violation of the principle of separation of duties and environments, which could introduce errors, conflicts, or malicious code into the production system. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Security Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 9: Security Management2; Types of Security Breaches: Physical and Digital3
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!