Question 1
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. 
Which of the following should the project manager do NEXT?
  1. Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
  2. Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
  3. Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
  4. Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Correct answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
Question 2
One deliverable failed during testing, and this has already happened several times. 
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
  1. Run chart
  2. Fishbone diagram
  3. Scatter diagram
  4. Gantt chart
Correct answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 322
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 322
Question 3
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. 
Which of the following documents would contain these items?
  1. Business case
  2. Requirements document
  3. Project timeline
  4. Task plan
Correct answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138
Question 4
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. 
Which of the following should a project manager update to document this information?
  1. A list of realized risks
  2. A list of decomposed activities
  3. A sequenced list of project tasks
  4. A document describing agreed-upon communication methods
Correct answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240
Question 5
The executive sponsor asks a project manager to summarize the following for a project:
  1. Final capital expenditures. 
  2. Anticipated cost of new employee resources to support the solution. 
  3. Maintenance estimates. 
Which of the following information should the project manager provide?
  1. Cost baseline
  2. Burn rate
  3. Cost variance report
  4. Total project cost
Correct answer: A
Question 6
Which of the following defines a group of projects that work together to achieve a common goal?
  1. Product
  2. Portfolio
  3. Program
  4. Project plan
Correct answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71
Question 7
A company hires an outside vendor to provide 24/7 support. 
Which of the following documents would determine the contractual obligations?
  1. PO
  2. SLA
  3. LOI
  4. MOU
Correct answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
Question 8
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. 
Which of the following techniques is MOST likely to be used to complete the project on time?
  1. Throttling
  2. Crashing
  3. Resource leveling
  4. Resource smoothing
Correct answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170
Question 9
A project manager is unsure if the quality of a deliverable from a SME meets specifications. 
Which of the following is the BEST way for the project manager to address the issue?
  1. Conduct a face-to-face or telephone meeting with the team member.
  2. Send an email outlining the concerns to the team member.
  3. Send a project team meeting to obtain feedback from everyone.
  4. Post the issue on the wiki page for input from stakeholders.
Correct answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
Question 10
Which of the following is a key aspect of the Agile project management methodology?
  1. Test-driven
  2. Daily standup meetings
  3. Short project durations
  4. Defined list of requirements
Correct answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
HOW TO OPEN VCE FILES

Use VCE Exam Simulator to open VCE files
Avanaset

HOW TO OPEN VCEX AND EXAM FILES

Use ProfExam Simulator to open VCEX and EXAM files
ProfExam Screen

ProfExam
ProfExam at a 20% markdown

You have the opportunity to purchase ProfExam at a 20% reduced price

Get Now!